Stage two of slope stabilisation work on the Kings Highway between Pooh Bear Corner and the top of Clyde Mountain will start next week, the Member for Monaro John Barilaro said.
Subscribe now for unlimited access.
$0/
(min cost $0)
or signup to continue reading
"The work is part of Roads and Maritimes' commitment to reduce the risk of rock falls on this important road to ensure it remains a safe and reliable route which serves the community well into the future," Mr Barilaro said.
"Stage one work was carried out last year to remove vegetation, rocks and boulders from the slope to increase stability and prepare for the installation of more permanent protective measures.
"Work on stage two will involve the installation of more robust fencing, rock bolts and netting. This will provide more permanent stability for the slope and is expected to significantly reduce the risk of future landslides onto the road.”
Work will be carried out on weekdays from 7am to 6pm and is expected to take about 15 weeks to complete, weather permitting.
Roads and Maritime is not planning extensive closures on the Kings Highway as part of this work which will be mainly carried out under single lane closures with motorists guided through the work site by traffic control.
Work will not take place on weekends or during times of increased traffic on Monday mornings and Friday afternoons. Work will also be suspended from Thursday 17 April to Monday 28 April to improve traffic flow during the school holidays.
Some blasting will be carried out as part of the work. To ensure safety for workers and motorists on the Kings Highway it will be necessary to close the highway for one eight hour shift in late April.
The closure will be carried out between 9am and 4pm.
Work is expected to be completed by mid-July, weather permitting.
Roads and Maritime is not planning extensive closures of the Kings Highway for this project.
The majority of work will be carried out under single lane closures, with motorists able to pass through the worksite under the guidance of traffic controllers.
Work location: The Kings Highway at Clyde Mountain between Pooh Corner and Government Bend.
Work times: Monday to Thursday between 7am and 6pm and Friday from 7am to 3pm.
Work dates:Monday 31 March until mid July 2014. No work will be carried out between 12pm Thursday 17 April and 12pm Monday 28 April 2014.
Traffic impacts: Single lane closures will be in place during work times, motorists should expect minor delays. All lanes will be open to traffic after work each day.
There is one full seven hour closure planned for late April which will be carried out between 9am and 4pm. The exact date will be communicated three weeks in advance. Detours are lengthy and motorists will be advised to avoid non-essential travel during closure times.
Please note - necessary emergency repair work to rock fall fencing will be carried out on Clyde Mountain at Pooh Corner Friday 28 March following a minor slip yesterday. Work will be carried out between 7am and 12pm (noon) under single lane closures. Impact on traffic will be minimal.